February 10, 2026 5:57 PM
To address deficiencies in our existing system, and to support continued growth and development, Bluffdale City has been working on a project to expand our storm water infrastructure east of the railroad tracks and north of 14600 South. A trenchless...
Storm Drain Outfall ProjectRead On...
Latest Update:
February 17, 2026 5:20 PM
As required by our permitting with the railroad companies, and in accordance with our permit from the County Health Department, work to complete the bore beneath the tracks will continue through this week during both daytime & nighttime hours.
We anticipate finishing the 24-hour boring work mid-day Saturday, February 21, if all continues as planned.
For concerns, you can email the project team at engineering@bluffdale.gov. Please note that emails are not monitored after normal work hours.